Submitter
Submitter: White, Jake | Organization: Joe White & Associates, Inc. |
Address: 25 Rahling Circle Suite A-2 | City: Little Rock |
State: AR | Zip: 72223- |
Phone Number: (501) 214-9141 | E-Mail: jakewhite@joewhiteassociates.com |
Project Information
Project ID: 131145 | Manager: Jake Chatman |
Received: 12/21/2023 12:00:00 AM | Due: 12/31/2023 |
Logged: 12/21/2023 | Closed: |
Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Open |
Summary: | |
Crystal Valley Trails Off-Site Water & Sewer, 15404 Crystal Valley Road, Little Rock**ONLINE** Fee $500 PD |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 12/21/2023 | Due: 12/31/2023 |
Date Completed: 1/3/2024 | |
Description: | |
C1 to JTC 1/3/24 |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 1/3/2024 | Due: 1/13/2024 |
Date Completed: 1/8/2024 | |
Description: | |
C1 to JTC 1/3/24 |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 1/8/2024 | Due: 1/11/2024 |
Date Completed: 1/9/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 1/9/2024 | Due: 2/23/2024 |
Date Completed: 1/24/2024 | |
Description: | |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 1/19/2024 | Due: 1/29/2024 |
Date Completed: 1/24/2024 | |
Description: | |
This project is connecting to a "future/by others" manhole downstream and cannot be approved until further information is obtained. The utility is LRWRA and the engineer resubmitted response that they have contacted LRWRA for a timeline and other construction details. I emailed the engineer on 1/24/24 concerning the comment. |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 1/24/2024 | Due: 2/3/2024 |
Date Completed: 1/24/2024 | |
Description: | |
This project is connecting to a "future/by others" manhole downstream and cannot be approved until further information is obtained. The utility is LRWRA and the engineer resubmitted response that they have contacted LRWRA for a timeline and other construction details. I emailed the engineer on 1/24/24 concerning the comment. |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 1/24/2024 | Due: 1/27/2024 |
Date Completed: 1/31/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 1/31/2024 | Due: 3/16/2024 |
Date Completed: 4/9/2024 | |
Description: | |
Assigned To: 210 | Action: Review, Comment and/or Approve |
Date Assigned: 4/1/2024 | Due: 4/11/2024 |
Date Completed: 4/9/2024 | |
Description: | |
C2 to JTC 4/9/24 |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 4/9/2024 | Due: 4/19/2024 |
Date Completed: 4/15/2024 | |
Description: | |
C2 to JTC 4/9/24 |
Assigned To: 210 | Action: Finalize and Send Letter |
Date Assigned: 4/15/2024 | Due: 4/18/2024 |
Date Completed: 4/15/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 210 | Action: Reminder to follow-up |
Date Assigned: 4/15/2024 | Due: 5/30/2024 |
Date Completed: | |
Description: | |