Submitter
Submitter: Burnett, Audrey | Organization: Swope Engineering |
Address: 7 Halsted Circle, Suite 210 | City: Rogers |
State: AR | Zip: 72756- |
Phone Number: (479) 877-7388 | E-Mail: audrey@civilfirst.com |
Project Information
Project ID: 120233 | Manager: Raymond Thompson |
Received: 5/2/2022 12:00:00 AM | Due: 5/12/2022 |
Logged: 5/2/2022 | Closed: |
Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Open |
Summary: | |
AP Willow Trace, Kelly Avenue, Tontitown**ONLINE** Fee $500 FEE PD 5/4/22 |
Assigned To: 153 | Action: Review, Comment and/or Approve |
Date Assigned: 5/2/2022 | Due: 5/12/2022 |
Date Completed: 5/11/2022 | |
Description: | |
C1Ltr 05/11/22 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 5/11/2022 | Due: 5/21/2022 |
Date Completed: 5/12/2022 | |
Description: | |
C1Ltr 05/11/22 |
Assigned To: 153 | Action: Finalize and Send Letter |
Date Assigned: 5/12/2022 | Due: 5/15/2022 |
Date Completed: 5/13/2022 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 153 | Action: Reminder to follow-up |
Date Assigned: 5/13/2022 | Due: 6/27/2022 |
Date Completed: 6/6/2022 | |
Description: | |
Assigned To: 153 | Action: Review, Comment and/or Approve |
Date Assigned: 6/6/2022 | Due: 6/16/2022 |
Date Completed: 6/15/2022 | |
Description: | |
C2Ltr 06/15/22 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 6/15/2022 | Due: 6/25/2022 |
Date Completed: 6/16/2022 | |
Description: | |
C2Ltr 06/15/22 |
Assigned To: 153 | Action: Finalize and Send Letter |
Date Assigned: 6/16/2022 | Due: 6/19/2022 |
Date Completed: 6/22/2022 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 153 | Action: Reminder to follow-up |
Date Assigned: 6/22/2022 | Due: 8/6/2022 |
Date Completed: 7/26/2022 | |
Description: | |
Send 30-day letter |
Assigned To: 153 | Action: Review, Comment and/or Approve |
Date Assigned: 7/26/2022 | Due: 8/5/2022 |
Date Completed: 8/5/2022 | |
Description: | |
C3Ltr 08/05/22 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 8/5/2022 | Due: 8/15/2022 |
Date Completed: 8/6/2022 | |
Description: | |
C3Ltr 08/05/22 |
Assigned To: 153 | Action: Finalize and Send Letter |
Date Assigned: 8/6/2022 | Due: 8/9/2022 |
Date Completed: 8/8/2022 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 153 | Action: Reminder to follow-up |
Date Assigned: 8/8/2022 | Due: 9/22/2022 |
Date Completed: | |
Description: | |
Send 30-day letter |