Submitter
Submitter: McEntire, Alan | Organization: |
Address: PO Box 524 | City: Vilonia |
State: AR | Zip: 72173 |
Phone Number: 501-944-2273 | E-Mail: |
Project Information
Project ID: 132368 | Manager: Jake Chatman |
Received: 4/16/2024 12:00:00 AM | Due: 4/26/2024 |
Logged: 4/16/2024 | Closed: 5/1/2024 |
Classification: Sub. Public Water/Septic Tank | Status: Closed |
Summary: | |
THE ORCHARD PHASE II 25 LOT SEPTIC SYSTEM PLANS, CONWAY AR. ONE SET OF PLANS SUBMITTED, $700.00 FEE PD |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 4/16/2024 | Due: 4/26/2024 |
Date Completed: 4/16/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 4/16/2024 | Due: 4/26/2024 |
Date Completed: 4/19/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 4/19/2024 | Due: 4/22/2024 |
Date Completed: 4/19/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 222 | Action: Reminder to follow-up |
Date Assigned: 4/19/2024 | Due: 6/3/2024 |
Date Completed: 4/26/2024 | |
Description: | |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 4/26/2024 | Due: 5/6/2024 |
Date Completed: 4/26/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 4/26/2024 | Due: 5/6/2024 |
Date Completed: 5/1/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 5/1/2024 | Due: 5/4/2024 |
Date Completed: 5/1/2024 | |
Description: | |
Project manager has approved this project. |