Submitter
Submitter: Hanson, Karl | Organization: Community Water System, PWA |
Address: Hanson & McLaughlin, LLC | City: Little Rock |
State: AR | Zip: 72205- |
Phone Number: (501) 716-2850 | E-Mail: karl_hanson@swbell.net |
Project Information
Project ID: 132119 | Manager: Jake Chatman |
Received: 3/25/2024 12:00:00 AM | Due: 4/4/2024 |
Logged: 3/25/2024 | Closed: 3/29/2024 |
Classification: Sewer Improvemnts(Non-Subdiv.) | Status: Closed |
Summary: | |
Edgemont Pump Station, 10373 Edgemont Road, Greers Ferry**ONLINE** Fee $500 pd |
Assigned To: 222 | Action: Review, Comment and/or Approve |
Date Assigned: 3/25/2024 | Due: 4/4/2024 |
Date Completed: 3/29/2024 | |
Description: | |
Assigned To: 192 | Action: Supervisor Review |
Date Assigned: 3/29/2024 | Due: 4/8/2024 |
Date Completed: 3/29/2024 | |
Description: | |
Assigned To: 222 | Action: Finalize and Send Letter |
Date Assigned: 3/29/2024 | Due: 4/1/2024 |
Date Completed: 3/29/2024 | |
Description: | |
Project manager has approved this project. |