Submitter
Submitter: Mejia, Alan | Organization: American Fire Protection Group, Inc. |
Address: 11121 Richardson Drive | City: North Little Rock |
State: AR | Zip: 72113- |
Phone Number: (501) 492-8550 | E-Mail: alan.mejia-santana@afpgusa.us |
Project Information
Project ID: 131042 | Manager: Dennis Taylor |
Received: 12/12/2023 12:00:00 AM | Due: 12/22/2023 |
Logged: 12/12/2023 | Closed: 2/14/2024 |
Classification: Water - Fire Protection | Status: Closed |
Summary: | |
Butter Scotch Fire Sprinkler, 104 E Central, Bentonville**ONLINE** Fee $50 pd |
Assigned To: 229 | Action: Review, Comment and/or Approve |
Date Assigned: 12/12/2023 | Due: 12/22/2023 |
Date Completed: 12/15/2023 | |
Description: | |
131042C1 dated 12-15-2023 |
Assigned To: 83 | Action: Supervisor Review |
Date Assigned: 12/15/2023 | Due: 12/25/2023 |
Date Completed: 12/18/2023 | |
Description: | |
131042C1 dated 12-15-2023. OK to mail/Email/upload to portal. DET 12-18-2023. |
Assigned To: 229 | Action: Finalize and Send Letter |
Date Assigned: 12/18/2023 | Due: 12/21/2023 |
Date Completed: 12/19/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 229 | Action: Reminder to follow-up |
Date Assigned: 12/19/2023 | Due: 1/18/2024 |
Date Completed: 1/10/2024 | |
Description: | |
Assigned To: 229 | Action: Review, Comment and/or Approve |
Date Assigned: 1/2/2024 | Due: 1/12/2024 |
Date Completed: 1/10/2024 | |
Description: | |
131042A1 dated 1-10-2024 sent to supervisor for review |
Assigned To: 83 | Action: Supervisor Review |
Date Assigned: 1/10/2024 | Due: 1/20/2024 |
Date Completed: 1/10/2024 | |
Description: | |
131042A1 dated 1-10-2024 sent to supervisor for review. Comments given to D5 Engr for follow-up. DET 01-10-2024. |
Assigned To: 229 | Action: Finalize and Send Letter |
Date Assigned: 1/10/2024 | Due: 1/13/2024 |
Date Completed: 1/12/2024 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 229 | Action: Reminder to follow-up |
Date Assigned: 1/12/2024 | Due: 2/11/2024 |
Date Completed: 2/14/2024 | |
Description: | |
Assigned To: 229 | Action: Reminder to follow-up |
Date Assigned: 2/14/2024 | Due: 2/17/2024 |
Date Completed: 2/14/2024 | |
Description: | |
Finalize and mail/Email/Upload approval letter to portal. DET 2/14/2024. |
Assigned To: 83 | Action: Supervisor Review |
Date Assigned: 2/14/2024 | Due: 2/24/2024 |
Date Completed: 2/14/2024 | |
Description: | |
Finalize and mail/Email/upload approval to portal. DET 2/14/2024. |
Assigned To: 229 | Action: Finalize and Send Letter |
Date Assigned: 2/14/2024 | Due: 2/17/2024 |
Date Completed: 2/14/2024 | |
Description: | |
Project manager has approved this project. |