Submitter
Submitter: Meyer, David | Organization: Freedom Fire Pro LLC |
Address: 811 Lester Ln | City: Rogers |
State: AR | Zip: 72756- |
Phone Number: (479) 631-6363 | E-Mail: djmeyer@freefirepro.com |
Project Information
Project ID: 130858 | Manager: Dennis Taylor |
Received: 11/27/2023 12:00:00 AM | Due: 12/7/2023 |
Logged: 11/27/2023 | Closed: 12/13/2023 |
Classification: Water - Fire Protection | Status: Closed |
Summary: | |
Cross Church Student Center Addition, 2448 S Pinnacle Hills Pkwy, Rogers**ONLINE** Fee $163.34 PD E-Payment |
Assigned To: 204 | Action: Review, Comment and/or Approve |
Date Assigned: 11/27/2023 | Due: 12/7/2023 |
Date Completed: 12/5/2023 | |
Description: | |
Sent 130858 C1 to DET for review Dated 12/5/23 |
Assigned To: 83 | Action: Supervisor Review |
Date Assigned: 12/5/2023 | Due: 12/15/2023 |
Date Completed: 12/5/2023 | |
Description: | |
Sent 130858 C1 to DET for review Dated 12/5/23. Comments given to D6 Engr. DET 12/5/2023. |
Assigned To: 204 | Action: Finalize and Send Letter |
Date Assigned: 12/5/2023 | Due: 12/8/2023 |
Date Completed: 12/6/2023 | |
Description: | |
Send comment letter and wait for a reply. Sent 130858 C1 to administrative staff for mailing on 12/6/23. Uploaded to the online plan review portal and notified David Meyer on 12/6/23 |
Assigned To: 204 | Action: Reminder to follow-up |
Date Assigned: 12/6/2023 | Due: 1/20/2024 |
Date Completed: 12/13/2023 | |
Description: | |
Waiting for response to 130858 C1 |
Assigned To: 204 | Action: Review, Comment and/or Approve |
Date Assigned: 12/7/2023 | Due: 12/17/2023 |
Date Completed: 12/13/2023 | |
Description: | |
Sent 130858 A1 to DET for review/approval Dated 12/13/23 |
Assigned To: 83 | Action: Supervisor Review |
Date Assigned: 12/13/2023 | Due: 12/23/2023 |
Date Completed: 12/13/2023 | |
Description: | |
Sent 130858 A1 to DET for review/approval Dated 12/13/23. Letter signed, plans stamped, OK to mail/Email/upload to portal. DET 12/13/2023. |
Assigned To: 204 | Action: Finalize and Send Letter |
Date Assigned: 12/13/2023 | Due: 12/16/2023 |
Date Completed: 12/13/2023 | |
Description: | |
Project manager has approved this project. Sent 130858 A1 to administrative staff for mailing on 12/13/23. Uploaded to the online plan review portal and notified David Meyer on 12/13/23 |