Submitter
Submitter: Dulin, Morgan | Organization: Crafton Tull |
Address: 901 N 47th Street, Suite 400 | City: Rogers |
State: AR | Zip: 72756- |
Phone Number: (479) 636-4838 | E-Mail: morgan.dulin@craftontull.com |
Project Information
Project ID: 130659 | Manager: Raymond Thompson |
Received: 11/6/2023 12:00:00 AM | Due: 11/16/2023 |
Logged: 11/6/2023 | Closed: 12/18/2023 |
Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Closed |
Summary: | |
TB Riverside Village Phase 2, Black Oak Road, Fayetteville**ONLINE** Fee $500 DUE |
Assigned To: 213 | Action: Review, Comment and/or Approve |
Date Assigned: 11/6/2023 | Due: 11/16/2023 |
Date Completed: 11/9/2023 | |
Description: | |
C1Ltr 11/9/23 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 11/12/2023 | Due: 11/19/2023 |
Date Completed: 11/12/2023 | |
Description: | |
C1Ltr 11/9/23 |
Assigned To: 213 | Action: Finalize and Send Letter |
Date Assigned: 11/12/2023 | Due: 11/15/2023 |
Date Completed: 11/14/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 213 | Action: Reminder to follow-up |
Date Assigned: 11/14/2023 | Due: 12/29/2023 |
Date Completed: 12/4/2023 | |
Description: | |
Assigned To: 213 | Action: Review, Comment and/or Approve |
Date Assigned: 11/27/2023 | Due: 12/7/2023 |
Date Completed: 12/4/2023 | |
Description: | |
C2Eml 12/4/23 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 12/5/2023 | Due: 12/14/2023 |
Date Completed: 12/5/2023 | |
Description: | |
C2Eml 12/4/23 |
Assigned To: 213 | Action: Finalize and Send Letter |
Date Assigned: 12/5/2023 | Due: 12/8/2023 |
Date Completed: 12/5/2023 | |
Description: | |
Send comment letter and wait for a reply. |
Assigned To: 213 | Action: Reminder to follow-up |
Date Assigned: 12/5/2023 | Due: 1/19/2024 |
Date Completed: 12/13/2023 | |
Description: | |
Assigned To: 213 | Action: Review, Comment and/or Approve |
Date Assigned: 12/7/2023 | Due: 12/17/2023 |
Date Completed: 12/14/2023 | |
Description: | |
A1Ltr 12/14/23 |
Assigned To: 84 | Action: Supervisor Review |
Date Assigned: 12/14/2023 | Due: 12/24/2023 |
Date Completed: 12/15/2023 | |
Description: | |
A1Ltr 12/14/23 |
Assigned To: 213 | Action: Finalize and Send Letter |
Date Assigned: 12/15/2023 | Due: 12/18/2023 |
Date Completed: 12/18/2023 | |
Description: | |
Project manager has approved this project. |