Submitter
Submitter: Wintle, Brian | Organization: Crist Engineers |
Address: 205 Executive Court | City: Little Rock |
State: AR | Zip: 72205- |
Phone Number: (501) 664-1552 | E-Mail: |
Project Information
Project ID: 111461 | Manager: Glenn Greenway |
Received: 5/22/2020 12:00:00 AM | Due: 6/1/2020 |
Logged: 5/22/2020 | Closed: |
Classification: Water & Sewer Imprvmn(Non-Sub) | Status: Open |
Summary: | |
WATER SYSTEM IMPROVEMENTS,CONTRACT II-BOOSTER PUMP STATION AND WATER TRANSMISSION MAIN, PARAGOULD LIGHT WATER & SEWER. ONE SET OF PLANS/SPECS SUBMITTED, $500.00 FEE PD |
Assigned To: 192 | Action: Review, Comment and/or Approve |
Date Assigned: 5/22/2020 | Due: 6/1/2020 |
Date Completed: 5/27/2020 | |
Description: | |
Assigned To: 192 | Action: Reminder to follow-up |
Date Assigned: 5/27/2020 | Due: 6/26/2020 |
Date Completed: 11/19/2020 | |
Description: | |
Assigned To: 104 | Action: Review, Comment and/or Approve |
Date Assigned: 6/1/2020 | Due: 6/5/2020 |
Date Completed: 6/4/2020 | |
Description: | |
Assigned To: 104 | Action: Reminder to follow-up |
Date Assigned: 6/4/2020 | Due: 6/14/2020 |
Date Completed: | |
Description: | |
Await response to comment letter. |
Assigned To: 104 | Action: Review, Comment and/or Approve |
Date Assigned: 6/15/2020 | Due: 6/25/2020 |
Date Completed: 6/17/2020 | |
Description: | |
Assigned To: 104 | Action: Reminder to follow-up |
Date Assigned: 6/17/2020 | Due: 6/27/2020 |
Date Completed: | |
Description: | |
Await response to comment letter. |
Assigned To: 104 | Action: Review, Comment and/or Approve |
Date Assigned: 6/19/2020 | Due: 6/29/2020 |
Date Completed: 6/22/2020 | |
Description: | |